|
|
Executive
summary for the collapseof Royal Plaza Hotel
|
E X E C U T I V E S U M M
A R Y
On the late morning of Friday the 13th August 1993, the most tragic
collapse of building in the history of Thailand took place in Korat,
Nakorn Ratchasima Province. The collapse took less than 10 seconds to
reduce the 6-storey complex into a mammoth pile of rubble, burying 379
unsuspecting occupants, killing 137 and badly injuring 227. The sights
of the rubble, the pitiful victims, and the strenuous rescue operation
will remain forever in the memory of most Thai people of this generation.
After the incident, all parties concerned, both public and private sectors,
expressed much interest in knowing the real cause, and in securing measures
for future prevention. A technical investigation under the Civil Engineering
Chapter of the Engineering Institute of Thailand (EIT) commenced immediately
upon the arrival of the Task Force at the site on August 15, 1994. In
addition to on-site inspection, technical data were collected and assessments
made of the nature of the collapse. These information together with
results of subsequent laboratory and model tests led to the conclusions
appeared in this report.
Moment of The Collapse
At approximately 10:10 am. on August 13, 1993, the six-storey building
of the Royal Plaza Hotel collapsed swiftly and totally, leaving high
only the front elevator hall, which was built with structural separation
from the rest. The collapse was mostly vertical and after the collapse,
leaving a neat floor-to-floor stack of concrete slabs. For structural
engineers, the impression of the collapse reminds of a professionally
torn-down building with the use of explosives. The entire building moved
downwards under its own weight within seconds and with no time to fall
sideways.
At the time of collapse, the building was occupied by 379 people. Among
them are 117 government officials from the Education Ministry were attending
a seminar in Benchamas Room on the second floor, 59 from Shell (Thailand)
in Pikul-Chuanchom Room on the fourth floor, and 78 as general hotel
clients. The rest are 125 hotel staff. At the end of the rescue operation
on September 3, 1993, it was reported 127 killed, and 227 injured
Historical Records
According to the construction permit granted in 1983, the original
part of the building, used as massage parlor, was 3 storey high plus
one underground level. Later in 1985, the local building authority approved
a construction permit to modify the building for use as hotel. But not
until 1990 that a permit was sought to add 3 more storeys to the original
buildings (see Figure 2 in Report). Checking from the calculation sheets
submitted by the structural engineer at the time of permit application,
there was no record of foundation and column strengthening. There was
no explanation how the modified structure could retain the same safety
standard after the addition of 3 more storeys. Later at the request
of the official, soil test was conducted by a local technical institution
to certify that the safety margin of the existing foundation was sufficient
in carrying 3 more storeys. No attempt was made further on the assessment
of safety margin of existing columns. The permit was granted nevertheless.
Method of Investigation
The collapse in Korat was rather uncommon for the following reasons:
(a) Most building collapses occur either during or just after the construction.
In this case, the collapse occurred about 3 years after the last modification.
(b) Most building collapses, after a long period of use, were caused
by unexpected forces of nature, such as earthquake, gust, etc. At the
time of collapse in Korat, however, there was no report of any harsh
environment, nor report of any misuse of the building to an extent that
can generate a devastating force of this scale that causes the swift
and total collapse.
After the incident, various aspects of investigation were conducted
by independent teams from Public Works Department (PWD), Asian Institute
of Technology (AIT), Chulalongkorn University (CU), Kasetsart Unversity
(KU), Khon Kaen University (KKU), and Engineering Institute of Thailand
with members derived from most universities and private consultants.
One conclusion agreed by all parties is that the structure of the
Royal Plaza Hotel was substandard, i.e., having marginal factor of safety,
after the addition of 3 more storeys.
The addition of 3 floor areas of dead and live loads over the same
set of columns that were originally designed to carry only 3 floors
means that the original safety margin could be reduced approximately
close to zero.
Normally safety of a building is generously provided in the process
of structural design. Because of the high factor of safety practiced
by structural engineers, even if one part of a properly designed building
is substantially overloaded and fails, redistribution of the loads will
take place. In such cases only local failures, but not a total collapse,
will result.
The case of the Royal Plaza Hotel was extraordinary as all columns were
nearly at their respective limit. This defies the belief that if a building
has survived past the construction stage, it is very unlikely that it
can collapse abruptly without major external forces, such as an earthquake.
Judging from the mode of failure, it can only be concluded that the
collapse started when all columns on the ground level failed nearly
about the same time, causing the entire building to fall under its own
weight. All these columns were overloaded and remained with only marginal
factor of safety. A failure of one column could easily trigger the rest
as the load carried by this column would be redistributed to the rest.
This subsequently caused them to fail, one after another, within a very
short time. This process is well known as "progressive failure". Within
a few seconds, all columns on the ground floor collapsed, and the 7000
ton mass of the central part of the building was unsupported. AT this
instance, it was like lifting the entire building 5 meters high and
letting it to drop under its own weight. The great impact caused a compressive
wave to the upper columns causing all of them to collapse shortly. From
observation during the removal of the debris, all columns at the ground
level burst almost into loose particles, a failure rather common in
the laboratory test of concrete cylinders. However columns from the
second storey up appeared to have buckled due to compressive wave after
the great impact. In addition, most of the survivors told of having
heard two distinctive loud noises seconds before the collapse. Presumably,
the first loud noise is due to the bursting of all ground floor columns,
and the next one due to the impact of upper-floor mass to the ground.
The First Failure.
In the professional point of view, no matter what triggered the
first column failure, the main reason for the collapse is the marginal
factor of safety after 3 more storeys were added to the building. Theoretically,
it is still interesting to find out the possible causes. To be able
to point them out, the Task Force of EIT have conducted the following
tests:
(a) Test of Concrete Strength. On-site test of concrete strength
using the non-destructive Ultrasonic Pulse Velocity Test (PUNDIT) revealed
that the tested concrete samples had a compressive strength in the range
of 10-15 MPa with 95 % reliability. This result did not, therefore,
point to any deficiency in the quality of existing concrete. This was
also confirmed by the laboratory test of concrete cylinders cored from
the remaining parts.
(b) Test of Rebars. Reinforcing steel bars collected from the
site were tested in the laboratory, and all were found to conform to
standard.
(c) Soil Test. The laboratory test of boring log from a location
in the vicinity of the collapse indicated that the bearing capacity
of soil in the area was sufficient for the foundation even after the
modification. Settlement based on the loading of 6 storeys is neglible.
Settlement due to consolidation or caused by subgrade water is unlikely,
judging from the composition of soil in the area. This conclusion coincided
with that of the investigation team from Public Works Department after
the debris over the area suspected to be the starting point was removed.
After excavation, foundation was found to be in good condition.
After eliminate other unlikely causes, the most likely cause of column
failure is due to creep in all ground floor columns under a high stress
level. After adding 3 more storeys, some columns on the ground level
carried a dead load up to 70-80 % of strength capacity. Under this sustained
overloading, micro-cracks developed in the concrete and, over the years,
they grew and propagated. The resulting creep deformation in these columns
increase gradually. As these columns crept and became shorter than the
neighboring columns, load was then redistributed to others, causing
other columns to be more overload and creep too. In this manner, loads
were redistributed back and forth over the period of 3 years until the
structural deterioration gradually spread over all columns on the ground
floor. When load in one column exceeded its capacity and collapsed first,
a progressive collapse of all columns on the ground floor followed and
completed within seconds. [1]
Lessons
Under the on-going economic fast-track experienced in Thailand,
economic consideration seems to be the main reason that can dictate
and deviate standard practices of many professions. While entrepreneurs
want to cash in with minimum investment efforts, they should be far-sighted
enough to invest a little more if this means a premium to prevent unacceptable
risks. Most important step for them is, therefore, to be able to appreciate
the independent advice of the right professionals. As far as the safety
of buildings is concerned, the best bet against this type of man-made
disaster is to acquire the service of an able and honest professional
engineers, who care more for the standard of the works than to obey
the architects and the clients.
Short-term Measures
Just after the incident, Prime Minister Chuan Leekpai visited the
site and ordered public universities to help review the safety aspect
of all buildings under suspicion throughout the country. All together
218 buildings were under investigation and a number of them received
recommendations for renovation. This measure was able to reduce public
concerns over the safety of existing buildings. In addition, a data
base of buildings around the country can be established in the process.
Long-term Measures
Because of the Korat man-made disaster, all parties in the engineering
profession expressed concerns over the current engineering practice.
They seemed to agree that the profession needs a major re-structuring.
Many meetings and seminars were organized afterwards with an attempt
to find the long-term measures. Although the current status of actions
is unclear to the Task Force at the time of preparing this report, the
following four points of actions have been discussed widely:
(1) Registration of professional engineers, who are allowed by law to
practice, must be more strictly controlled.
(2) If (1) is not effective, indemnity insurance system must be established.
(3) If (1) is not effective, design of all public buildings must be
cross-checked and jointly responsible by an independent third-party
engineer.
(4) Usage of public buildings requires a license which must be renewed
every 5 or 10 years.
Establishment of Engineering Council
Currently, all building construction works are controlled by the
Building Control Act 2522/2535 (1979/1992), and engineers must register
to practice under the Engineering Profession Act 2505 (1962).
Under the Building Control Act, the authority who exercises the control
of "works" is the Office of Building Control Committee, an affiliation
with the Public Works Department. By the Engineering Profession Act,
the authority who exercises the control of "professionals who conduct
the works" is the Office of Engineering Profession Control Committee
under Interior Ministry.
When a registered professional engineer submits engineering drawings
in the application of construction permit, he must also accompany with
a set of engineering calculations. It is stipulated in the Building
Control Act 2522/2533 that local building authority need not verify
these calculations.
The idea is to allow a registered professional engineer to take the
full responsibility of his work. On the other hand, this also implies
that a decision made by one single person may decide the fate of hundreds
of lives in the building, a case of Royal Plaza Hotel disaster. The
screening, qualifying and ethical control of professional engineers
are therefore crucial in reducing the risk of similar incidents. This
can be done effectively if the screening party also represent members
of the same profession. A strong proposal is therefore the establishment
of "Engineering Council" with a mechanism for its members to
protect, control and look after the profession. This is also along the
policy of the current government in bringing the private sector to support
public interests. The same recommendation was also given in a report
on "Strengthening Disaster Management Strategies in Thailand",
a study by Asian Disaster Preparedness Center, Asian Insitute of Technology,
for Royal Thai Government supported by the United Nations Development
Programme.
Members of the EIT Task Force Task Force
Worsak Kanok-Nukulchai (Chairman)
Mhan Sriroenthong (Secretary)
Noppadol Phien-wej
Krai Tangsanga
Anek Siripanichkorn
Pennung Warnichai
Poonsak Piansusom
Boonchai Satitmanaitham
(Completion Date: September 30, 1994)
[1] Similar explanation was used for the cause of
collapse of Hotel New World in Singapore on March 15, 1986. Chairman
of the EIT Task Force wishes to thank Professor Sang-Lip Lee, who was
a member of the Commission of Inquiry into the collapse of Hotel New
World, for the opportunity to discuss this matter with him.
|
|